Mysore/Mysuru: The long-pending proposal to increase the runway at Mysore Airport from the present 1,740 metres to 2,750 metres within the first section, a transfer that may allow the operation of bigger plane, has gained recent momentum.
The Airports Authority of India (AAI) has initiated a joint survey and inspection of 206.12 acres recognized for enlargement. The train is aimed toward verifying land boundaries, assessing website circumstances and figuring out any encumbrances earlier than documentation is finalised.
A multi-agency inspection was carried out between Dec. 15 and 17, 2025, involving officers from the Karnataka State Industrial and Infrastructure Improvement Company Restricted (KSIIDC), the nodal company for land acquisition and handover, together with the Karnataka Industrial Areas Improvement Board (KIADB), Cauvery Neeravari Nigam Restricted (CNNL), Karnataka Energy Transmission Company Restricted (KPTCL), Nationwide Highways Authority of India (NHAI) and the AAI.
Throughout the inspection, a number of lacking boundary stones had been observed within the earmarked space. Earlier than continuing with the acquisition, AAI authorities wrote to KSIIDC searching for a re-survey to obviously establish and demarcate the land and facilitate its handover.
The re-survey was subsequently performed from Feb. 9 to 12, 2026, in Marase and Mandakalli villages within the presence of AAI officers, a senior Geographic Data System (GIS) analyst from AAI and a KIADB surveyor. Boundaries had been measured on-site close to JMC maps and duly marked.
In response to an AAI press notice, boundary markers have now been restored and stones laid appropriately.
KSIIDC is required handy over the land to AAI freed from encumbrances, at the same time as residents and landowners have acknowledged that compensation for buildings, homes and timber is but to be acquired.